Network of Stand-by Oil Spill Response Vessels: Drills and Exercises. Annual Reports
-
Published05.04.2017
-
Updated23.03.2018
Number of vessels which can be mobilised simultaneously: 18
Average storage capacity per vessel for recovered oil: 3.500 m3
Network storage capacity, if 18 vessels are mobilised: 60.000 m3
Number of related equipment stockpiles: 18
Mobilisation time (vessel ready to sail to site) after request: 24 hours
Mobilisation procedure:
-Member States request assistance via the ERCC
-Member States have operational control of the vessel during the incident
![]()
Supporting Pollution Response for Cleaner European Seas
EMSA Network of Oil Spill Response Vessels - Protecting European Seas against Pollution